ECT Euromax intake station

On Maasvlakte, we are constructing a 66 kV intake station. This facility is a critical part of the energy infrastructure required to enable the shore power system for the ECT Euromax terminal. The new intake station will be connected to a converter station that adjusts voltage and frequency levels, making shore power suitable for vessels at berth. We are working together with Heijmans on the preparation and construction of the grid connection station. Heijmans closely collaborates with project partners Cordeel, responsible for the civil design and construction works, and Stedin, responsible for the electrical installation.

Since

2026

under construction

Schedule

Q3 2026: Start of construction of the intake station
Q1 2027: Civil works completed by Heijmans
Q1 2027: Start of electrical installation works by Stedin
Q1 2028: Completion of the high-voltage installation for the Euromax shore power facility

Leo Ruijs, CEO van ECT: ‘De ontwikkeling van walstroom sluit goed aan bij de doelstelling van ECT om vanaf 2035 emissievrij te zijn. ECT klanten kunnen bij hun bezoek aan onze terminals beschikken over walstroomfaciliteiten, die goed passen binnen de filosofie van ons logistieke concept’.

Facts & Figures

Total power

50 MVA